Hi Gurus,

I have a scenario in my company whereby customer return a faulty FGD for replacement.

We will then create a PO to ask vendor for free replacement for that component of the FGD which is faulty. We will also create a production order to take existing component stock and build into FGD and deliver to customer.

Now the issue is with the MAP. When performing settlement, the cost of the production order is inflated as it is taking into consideration component stocks that have been valuated, rather than the zero cost stocks that the vendor can deliver only months later. Is there a way that I can revalued only the stocks that I use in the production order to be zero, beside using MR21 which is to revalue the whole Plant stock ?

If you have a separate replacement process, pls let me know also.