PRT Material consumption for a Production order

Dear Experts,

I need an information on PRT material Consumption for Production order.

I have created the 2 PRT Material ( Greese & Alloy) with FHMI material type.

Assigned this PRT Material to Routings with Quanitity to 3 operations.

PRT materials will be procured on the MRP data, so stock is there in the plant & particular storage location.

So Production order will be created for FG material, so when I confirm the production order system is not consuming this PRT material.

Pl note -- Here our PRT material is not tool/equipment it is consumable material, but here considered as PRT material.

How the system will consume this PRT material once Production order is confirmed and goods are issued.

rgds

GSC

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    avatar image
    Former Member
    Sep 25, 2008 at 05:55 AM

    Hi,

    I doubt PRT can not be consumed. Because system will treated it like tool or machine.

    Becuase we are assigning PRT to the operation like work center.

    If u want to consume PRT, then try to put it in the BOM as component and check.

    It may consume.

    Regards

    Vijay

    Add comment
    10|10000 characters needed characters exceeded

    • Dear,

      PRT' s are used as a tools which are used during the production. So they are not consumed.

      First create the PRT with material type FHMI

      Then you have to assign this PRT in particular operation in the Routing.

      The PRT always reusable.

      Go to CO02 (Production order) in operation view at bottom there is option for PRT.

      You can do the availability check for PRT also . PRT has usage and formula on that basis it can be utilize in production.

      Only PRTs will have the maintenence plans and calibration plans thats all .PRT will not have any consumption in production

      You have to maintain availability group in material master.

      Then in transaction OPJK - order control, cehck the availability check settings for PRT's

      Hope clear to you.

      Regards,

      R.Brahmankar

  • avatar image
    Former Member
    Jan 10, 2011 at 07:18 AM

    Dear GSC,

    I am also facing the same issue that how u maintain the consumables as PRT's For EX: Grinding Wheel

    Please help on this.

    Regards,

    Vimal

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jan 23, 2011 at 09:15 AM

    Dear Experts,

    I want an information regarding how to map consumable material say for eg: Grinding wheel, scribber in mechanical engineering industries.

    As according to our knowledge if we are creating in the concept of material PRT's means how we will maintain their life and how according to that procurement activities happened to that particular material and how i come to know that consumes happened against production order.

    regards,

    Vimal

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Dear DG49,

      Thanks for your reply.

      Our client is manufacturer of cutting tools, punching tools etc. for manufacturing these kind of tools they need grinding wheel, scriber for that operation. so we suggested to create as consumable prt because the same grinding wheel is used to manufacture different tools.

      In this case of grinding wheel how to consume and update the stock.

      Please suggest the configuration settings for this scenario.

      Regards,

      Vimal