planing calender

hi

i want to create planing calender ,in that acutal period coulm is there ,wat is the critiria behind that to fill up

can anybody explain me in the planing calender creation

Edited by: praveen n on Sep 24, 2008 9:19 PM

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Sep 24, 2008 at 07:32 PM

    Hello Praveen,

    Please check below sap help link

    [Planning Calendar|http://help.sap.com/saphelp_47x200/helpdata/en/f4/7d25f744af11d182b40000e829fbfe/content.htm]

    Regards

    Pradeep

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 25, 2008 at 04:32 AM
    Add comment
    10|10000 characters needed characters exceeded

  • Sep 25, 2008 at 04:47 AM

    Dear,

    You can create Planning calander in MD25,

    Menu path: Production -> MRP -> Master Data -> Planning Calendar (MD25).

    You need to assign this calander in MRP 2 view of material master with lot size PK.

    Planning calender is used to define flexible length of period.

    You can define your planning period with planning calender.

    When creating planning calender you can define valid upto date & also period start from which day ex. week start from tuesday or thrusday.

    If you want to plan a material for every thursday, you can use this.

    Hope clear to you.

    Regards,

    R.Brahmankar