ChaRM: Schedule /TMWFLOW/SCMA_TRORDER_IMPORT/000 hourly

Hi!

Does the task "Import transport request (background)" in task plan of CharM import all the released transports from normal corrections and urgent corrections?

Are there some possibility to plan them hourly or more then daily?

If Yes, how?

Thank you very much!

Thom

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Sep 25, 2008 at 08:19 PM

    Hi Thom,

    you go to your task plan (SCMA), right click on Import Transport Requests (Background) > click Schedule, and setup the schedule you want to run it on.

    regards,

    Jason

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      hi

      try the following.

      schedule the job once as mentioned above.

      go to SM37, find and copy the job.

      repeat scheduling with the period you like.

      kind regards

      markus