Hii MM Gurus,
I am going to take external service for making repair of the pump. For repair i am going to send pump & some bearing out for repair of the pump. I am following the process as follows which is out of SAP (Not yet configured). The process is as
1. I make refurbishment order for pump & also assign other material.
2. I make goods issue from store on order & then sends goods to supplier.
3. I am making issue to order but the next operation that is sending material to vendor after goods issue is out of sytsem as for doing 541 material should be in stock & i have already posted it on order.
So what should i follows or how i should post the material sothat it will get issue to order & also post the movements sothat it will allow me to send it out to vendor?
What process i should follow sothat i can show the material is received from vendor & then Repaired pump is available in store for use?
Regards
Makarand