IN a particular operation i need to confirm at 2 points in the entire operation and at the end of the operation. so i have to do 3 confirmations at 20 60 80. 80 is my final operation.so will all there three confirmations be milestone confirmations.but if i dont do the confirmation at 20 the system should not allow me to do the 60 confirmation.
but if i make all the three operations as milestone confirmations if i confirm at 60 confirmation. then the 20 operation also will be confirmed.can i confirm an operation at 20 with out confirming at 10.if the confirmation is not milestone.
how to do this help meout.
where do i make a confirmation a milestone confirmation.
i think we will be having an option in the control key.