Finished Goods planning type set to ND (in the MRP view 1) but still in the MRP ?

Apr 11 at 03:06 PM

27

avatar image
Former Member

Hi everyone!

Do someone know the potential reasons for this scenario :

we set some item planning type to ND but after we run the MRP, we still avec planned orders for them and purchase requisites for their BOM.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Caetano Almeida
Apr 11 at 03:08 PM
0

Hello

A material with MRP type ND should no longer be planned by MRP, since the planning file is deleted. However, MRP dependent date, such as existing planned orders, MRP lists and purchase requisitions won't be deleted and you should delete them manually.

Did you already try to delete all the MRP dependent data and run MRP again? Did you check the MRP List to see when this material was planned for the last time?

Try to delete all the dependent data and run MRP again for this material.

Regards,

Caetano