Hello,

We are in SRM 4.0 and working on local SRM Contract.

Now we want to update the validity in these contract, but as there is no way to perform mass change to these contract.

Is there any way we can update the contract validity period at the header level and also at the Item Condition level.

Thanks & Regards,

Hitendra

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Hitendra,

Please go through the following link:

Thanks,

Pradeep

Former Member
0 Kudos

The transaction BBP_CTR_MASS doesnot exist in SRM 4.0

The Validity period for this contract will expire soon and we want to update the contract Validity period as the number of Contract are in Thousands and each contract consists of many line items.

Regards,

Hitendra

former_member183819
Active Contributor
0 Kudos

Hi

It is not advisable to update contract validity period as per the standard process.

BBP_PD_CTR_UPDATE - You try this FM to update contract but i am afraid since you are trying to update the validity period.

reagrds

Muthu