Sep 23, 2008 at 07:08 AM

Scheduling of maintenance plan

20 Views

Hello frds,

I have created a maintenance plan with following details:

Cycle unit : 3 day

Call horizon : 100%

scheduling period : 10 days

I have done the scheduling using IP30 and it created 3 notifcations. My issue is all the 3 notifications have same notification date for ex:

IP 30 running date: 23.09.2008

As per the above it shouls have created 3 niotifications with date as 23.09.2008, 26.09.2008 and 29.09.2008. But it has created all the notifications on the same date and also the notification is not released.

Can some one guide.

Regards,

Narendra