Dear PP Gurus,
My order is 30000 qty. I used operation splits & overlaping. In first work center out of 6 splits used 1 split & 2500 qty. overlaping, in second work center out of 370 splits used 30 splits & 6000. In third work center no splits & no overlaping.
When I am creating production order with forward schedulling ( forward is the requirement), how many times I am clicking on schedulling that much times dates are changing. I don't know why? please please explain
Jayesh Narvankar
SAP PP