Dear Expers,
we have a situation wherein we have one revision, 2 notifications, same task list, but 2 different equipments.
When we try to create orders thru MEB, error encountered.
However when deassigning 1 notification and leaving only one in the revision, order generated successfully.
Is it really the process that orders will not be created if same task list and different equipments were assigned in one revision?
Please advice.
Thanks!
Hi,
In MEB, Orders can be created for same tasklists for the assigned notification in the revision.
Regards
Anil Kumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Hasim,
An Order be created for n no. of nitification and n no. equipments. There is a tab in order Objects there you can see.
If you creating an order for 10 notifications and different equipment and task list then it will all be club into object tab of order. And one of these notification can be header notification.
I hope your doubt is clear or revert back.....
Regards,
Kaushal rai
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.