Planned Cost for Internal Actvity

Dear All,

I am not able to get plan cost of internal actvity., after adding work center...

it's giving me followning error in cost calculation...

"In the routing for this material, operation 0010 (and possibly sub-operation ) points to work center MD01 in plant 6001. However, no cost center has been assigned to this work center. (Activities are valuated using the activity prices in cost center accounting to calculate the planned costs for an operation.)"

I have maintained cost center in work center also assign actvity type for it in KP26.

Also, i am not getting Default tab while creating work center in CNR3.

Please, let me know the reson for this if possible.

Thanks and Regards,

Atul R. Rajmane

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Sep 23, 2008 at 03:45 AM

    hi

    check what is the workcenter maintained in the sub operation also .kindly check whether the planned values for cost center and activity type is specified in the workcenter master data

    also check in T code OP13 whether default tab is activated

    regards

    thyagarajan

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 23, 2008 at 04:01 AM

    hi

    pl check the worcentre assinged to sub operation whether that work centre is having cost center.

    -ashok