Hi Experts,

Partial Confirmation plus Partial Rejection from Ariba(Suppliers network) could not be processed.

Steps to Reproduce:

1) Create a purchase order.

2) Confirm some part of the quauntity and reject the balance part in Ariba.

3) Open the link in SRM and click Copy push button.

4) Click on Process PO and check PO, the PO is not updated with the changes done in Ariba

Expected Result:

PO should update the changes done in Ariba.

Here when part quantity is confirmed and part is rejected at Ariba, its sending a POR but SRM is not updating anything for non-catalog items when POR is copied onto PO.But where as in the Catalog items partially confirmed POR is copied onto PO.

kindly give your valuable inputs to poceed furthur.

Regards,

Chandu

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

I think this question should be posted in the SRM Forum. You will get your input there.

Thanks