on 04-11-2018 2:42 PM
SAP B1 9.2 PL7
Timesheets & projects (costings).
After creating a timesheet & linking it to an existing project. Is there any way to have the costs on the timesheet included in the project? At the moment the labour cost hours on the timesheet are not included in the Project costs?
(You can see the timesheets using Timesheet report within the project but the values do not appear in the overall project)
Is there a way I can use the time sheets to include labour costs on a project?
Previously it was suggested to use a work-around via production order, where you can assign resources to a production item (fictitious labour costs item). You can add these production orders to the project and so add the labour costs to the project. Its not an ideal solution so want to know has this changed in later patches or the new 9.3 release?
Thanks
Going to use the previous suggestion - work-around via production order, where you can assign resources to a production item (fictitious labour costs item). You can add these production orders to the project and so add the labour costs to the project.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.