Hi

Is it possible to transfer

Revenue Surplus

Revenue in excess of billing

calculated cost of sales

to COPA value fields.

We get the above values once we do RA on projects. I want to know whether we can capture this in COPA.

If answer is no then what is the reason for not being able to do it.

Regards,

Reddy

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Sep 23, 2008 at 01:47 PM

    Hi, Yes, by all means, it is possible to transfer to COPA. You need to configure PA structure for passing the values to the relevant value fields by creating different assignment lines for which you need to input the source cost element and target value fields. And this configured PA structure shall be assigned to the settlement profile. The standards are for PA transfer structure is '30-Sales orders/Project and for Settlement profile is SD1. Trust this helps much! Cheers!

    Add comment
    10|10000 characters needed characters exceeded

  • Sep 23, 2008 at 04:58 AM

    hi reddy,

    you can settle these costs to CO-PA. It will not pass to CO-PA while billing.

    Regards,

    Abhisek

    Add comment