While taking Mrp Run , routing Machine time is not considered for semi finish goods planned order
Case
There are 4 processes to convert raw material to finish, defined 4 semi finished items and there routing with Machine Process time, following parameters are mention for each semi finish item
u2022 Routing has base quantity of 1 EA and machine time as 120 Min.
u2022 Schedule margin key = 000 i.e all the float values is zero
u2022 In-house processing time in material master is 1 day
All 4 item planned order start date and finished date is the same.
Pls. guide.
Prakash