on 09-22-2008 1:43 PM
Hi All,
Please let me know how to reset the Release Strategy of PO, whenever the Terms of Payment Key value id modified.
Thanks in advance.
Regards
Naveen
Hi,
This is not possible in SAP standard.
You have to use User Exit;
M06E0004 - Changes to communication structure for release purch. doc.
And Function Module;
EXIT_SAPLEBND_002 - Changes to Communication Structure for Release of Purchasing