MRP run problem

53 Views

Hi experts,

During MRP run for a material , open PO quantity is not considered If delivery date mentioned in that open PO exceeds 110 days from planning date(MRP run date). If it is less , it considers open PO quantity.

MRP type = V1 (Reorder point planning)

Lot size = HB

planned delivery time = 0 days

What could be the reason for it? Pls help me out.