Hello together,
I am facing one serious issue at my client. While extending or creating new material, our planning dept.use to maintain profit center as dummy
but this dummy profit center is no more active at our plant.
We can able to create PO as well as MIRO with material no which having dummy profit center but while doing MIGO, system gives me following erro message.
: Account 694005 requires an assignment to a CO object"
It is very difficult in case if the MIRO has done casue this error occures while doing MIGO so but natural i have to cancel the entire MIRO which i think a big headche job.
Can any one suggest me the