Skip to Content
avatar image
Former Member

raw material consumption.

Hi Experts,

I am getting an "Invalid factory calender" while posting raw material consumption thru MB1A.

My calender contains five workings day and one public holiday. Even after i made six working days i am not able posting rawmaterial consumption while saving the screen i am getting error. Even i am trying to posting on working days i am getting error.

Please provide solution

Thanks and Regards

Balu

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Sep 22, 2008 at 07:58 AM

    Hi

    step 1: Check your factory calendar in T.code : SCAL if not defined ,please do it

    Have you assginged factory calendar to your plant?

    Assignment of the factory calendar by plant is done in transaction code 'SM30 - V_T001W'

    Hope it solves the issue.

    Add comment