on 09-22-2008 8:15 AM
Hi Experts,
I am getting an "Invalid factory calender" while posting raw material consumption thru MB1A.
My calender contains five workings day and one public holiday. Even after i made six working days i am not able posting rawmaterial consumption while saving the screen i am getting error. Even i am trying to posting on working days i am getting error.
Please provide solution
Thanks and Regards
Balu
Hi
step 1: Check your factory calendar in T.code : SCAL if not defined ,please do it
Have you assginged factory calendar to your plant?
Assignment of the factory calendar by plant is done in transaction code 'SM30 - V_T001W'
Hope it solves the issue.