MRP planning run

17 Views

Hi experts,

During MRP run for a material , open PO quantity is not considered If delivery date mentioned in that open PO exceeds 110 days from planning date(MRP run date). If it is less , it considers open PO quantity.

What could be the reason for it? Pls help me out.

Thanks in advance,

Rgds,

jay