Change schedule line date during MRP run

Apr 10 at 12:28 PM

21

avatar image

Dear,

We have a requirement where we need to change the proposed schedule line date during MRP run (for scheduling agreement lines only). We have several automotive JIT facilities, and if one of our customers shut down for a period, then we want to shift dates forward / backwards so we do not schedule any schedule lines within that period. We do not want to change the calendar every time this occurs because we simply do not know well enough in advance.

My idea was to create a simple z-table where we can add the plant code and from/to date we need to have a buildout / shutdown. Then when MRP runs it should check if the schedule line date is within this range, if so then move it forward/backwards.

I know there is a ton of badi's / exits out there for MRP, but I have not been able to achieve this. Only way I managed to make it work is to update the part number with a new safety lead time, which is not really a good route to take since we'd have to be changing part numbers all the time.

Does anyone have an idea where to look?