PCNF status

Former Member
0 Kudos

hello all

When I confirm one of the operation in an order the order status is PCNF and if confirm final operation with partial quantity then also order status is PCNF. I want to separate out how many operation confirmed and what are the quantities being confirmed. Please give suggestion for the same.

warm regards

Accepted Solutions (1)

Accepted Solutions (1)

dhaval_choksi3
Active Contributor
0 Kudos

Hi,

You can distinguish it by using COOIS / COOISPI and execute the report for Operations. Do changes in layout by introducing System status and confirmed yield fields in the report.

Regards,

Dhaval

Answers (2)

Answers (2)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hi,

You can check in operation overview of production order itself with status inCO02.

Regards,

R.Brahmankar

Former Member
0 Kudos

Hi,

You can see all operation wise confirmation details with quantity etc. in :

Tcode : CO14 ( Display Production order Confirmation: Actual Data)

Revert if any doubt.

Regards,

Tejas