on 04-10-2018 9:41 AM
Hi Experts,
I have a question. Can we manually create production orders without planning run in SAP ByD. I tried and searched in the help center but was not able to get a solution.
Regards,
Abhishek
Dear Abhishek,
You can create production orders without planning runs. However, stand alone production orders cannot be created. You will have to follow the below given steps to create production orders without planning runs.
I hope this helps. Have a great day.
Regards,
Anand
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Anand,
Thanks for your reply.
Yes the solution which you have given will be too lengthy for manual creation as we have to follow the planning cycle for every manual creation production orders as in my case the requirement for creating manual production order is frequent.
Regards,
Abhishek
User | Count |
---|---|
102 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.