edit production order for scheduling

Hi PP Gurus,

I have to address following requirement in SAP PP -

1.Factory calender defined at plant level for 6 working days.

2.work center working time defined for 9.00 hrs.

3.production order created for certain qty. now due to some urgency I want to plan the activities for this particular order on sunday for 24 hrs.

Condition -

1.I do not want to apply special rule in calender because it will be applicable to other orders also.

2. I do not to make the changes in work center master because it will be applicable to other orders also.

3. I am ready to make the changes in specific production order.

Please suggest if any way out to make the working period in production order without touching master data.

Regards,

Abhay

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Sep 20, 2008 at 08:24 PM

    Change the scheduling type as = Only for capacity requirement and enter teh start and end scheduled date manually and save.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Sep 21, 2008 at 06:19 AM

    Hi,

    You can define the shife intervals for that particular day only and the **** timings also u can mention as per your reqmt. This will be applicable for that particular day only.

    Regards,

    V. Suresh

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Sep 22, 2008 at 05:31 AM

    Dear,

    Best way you need to define shift sequence OP4A and assign it to your relevant work center for particular valid period of time and then So go in work center in capacities screen define your interval of avilable capacity there, you will get option workdays there you have to select :- Working days (overrides factory calendar).

    After that scheduling will take place on Sundays also.

    After that create production order then you will be able to schedule an order on sunday.

    Factory calendar will be remains same but scheduling will be take place on sunday for particular validity period of shift sequence as you maintained in work center.

    Hope clears to you.

    Regards,

    R.Brahmankar

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.