Hi PP Gurus,
I have to address following requirement in SAP PP -
1.Factory calender defined at plant level for 6 working days.
2.work center working time defined for 9.00 hrs.
3.production order created for certain qty. now due to some urgency I want to plan the activities for this particular order on sunday for 24 hrs.
Condition -
1.I do not want to apply special rule in calender because it will be applicable to other orders also.
2. I do not to make the changes in work center master because it will be applicable to other orders also.
3. I am ready to make the changes in specific production order.
Please suggest if any way out to make the working period in production order without touching master data.
Regards,
Abhay