Friends,

While doing planning transfer to activity planning through KSPP the issue is like this .

Plan is updated in MD61 , and then KSPP is run using a planning scenario with version in which plan is updated

KSPP has run successfully giving cost centre wise/material wise planned activities

issue is after KSPP run whne we check in KP26 -activity planning for cost centre , instead of the plan activity should get updated with the KSPP out put it is getting displayed as Activity Scheduled .

is there any other customization or some transaction is to be run to get these activity scheduled (out put of KSPP transaction) to get updated in Plan activity field of KP26

please provide inputs

regards,

madhu Kiran