Distribution of Available Capicity at Workcenters

Former Member
0 Kudos

Dear Guru's

We are facing problem when issuing Production Order on the basis of Current Date.

The proposed date is calculating on the basis of only 1 shift & 1 machine. While we

have 5 machine at a same workcenters. for e.g capcity of 1 machine is 30,000 units

& we have 2 machine so available capicity is now 60,000 units. When we issued production

& check the capacity avail & req qty. It shows like this ..

Date Req Qty Avail Capicity

15.09.08 30,000 60,000

16.09.08 30,000 60,000

We want to utilize full available capicity in a same day. The distribution % of capicity is 100%.

Can any1 answer plz?

Regards,

RM

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hello,

You have to spilt the work between the number of available capacity. since you have already created production order, goto to opeartion over view , for each opeartion assign the number split equal to as individual capacity assigned at workcenter.Now schedule order and check with CM01.

or

In your material routing click on operation.Under splitting tab,click on required splitting.Give number of splits(equal to capacities then use the READ PP MASTER DATA FUNCTION at Production Order/.

Regards

Pradeep Kumar

Former Member
0 Kudos

I have defined the no. of individual capicities in spilliting too. but still its doing same.

Wat is missing now?

Regards,

RM

Former Member
0 Kudos

Dear Pardeep,

I followed your instructions, but nothing change here its all same. Wat is missing? Can you give me some clues to check?

Regards,

RM

Former Member
0 Kudos

Hello Rasid,

What i have understood is you have created two production orders, the second order scheduled in next day, even though the previous day have enough available capacity.Since u have assigned no of spilt , lead time of order should have been reduced. Now u have to reschedule the second production order to previous day.

In that case do the capacity leveling for second order at Cm21/CM25. Before that activate finite scheduling check box at capacity header of the workcenter for which Prod order created.

Then check with capacity overview at cm01.If i am wrong please explain with examples

Regards

Pradeep