Why basic dates are displaying more extra dates by compare to production dates in production order

1.jpgHi Experts,

Please help us to resolve the basic dates issues in the attached planned order, where we are getting excess dates.

PFA screen shots1

.jpg

2.jpg (178.5 kB)
1.jpg (123.2 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Apr 11 at 01:09 PM

    Hi Bharani,

    Have you maintained any float after production in scheduling margin key, check it detailed scheduling tab in planned order.

    Definition : float after production
    Number of working days planned in scheduling as a safety buffer between the scheduled finish and basic finish date of an order.