Package Sequence for Calibration maintenane

Hi Gurus,

For doing calibration my client wants to define the packages in the follownig way

10 1 WK 1st Week 1W 1 A

20 2 WK 2nd Week 2W 2 B

30 1 MON One Month 1M 3 C

40 2 MON Two Months 2M 1 D

50 3 MON Three Months 3M 2 E

60 6 MON Six Months 6M 3 F

70 1 YR One Year 1Y 1 G

Now the requirement is like that in the period of 1 Year every package should be performed once only. i.e. it should not be repeated i.e. 1st package should be performed only when the last one is completed.

Please give your valuable inputs.

Regards

Pankaj

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Sep 19, 2008 at 10:44 AM

    Dear Pankaj,

    Not for the format you have given. In in packages creation you can go only for one unit. So better you take Days (UOM) for this kind of requirement.

    Eg. 7 Days

    14 Days

    30 Days etc....

    Regards,

    Kaushal Rai

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.