on 09-19-2008 10:55 AM
Hi,
We are using MTO senario. I am including packing material in BOM.
So How can i control, material I entered in BOM is same as material I am using for Packing is same when I am doing packing in delivery process?
Also I want if I am using different materail for packing purpose , its value & stock need to be updated.
Any suggestion ???
Regds,
Chetan
closed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Including a packing material in BOM will not anyway affect the process.
You can again pack one packing material using another material.
So in delivery, you can use the same packing material to pack your finished good(which includes your packing material also). You can also pack your finished product using some ohter packing material which is not a part of your BOM.
Hope this helps
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.