Skip to Content
0
Former Member
Sep 19, 2008 at 08:31 AM

Requirement planning strategy 11

32 Views

Hi,

I have to do gross requirement planning. For this I have done following settings:

Maintained strategy group 11 on the MRP screen.

Set the Mixed MRP indicator to 2 on the MRP screen.

Maintain the item category group ( NORM) on the Sales Organization screen.

Maintain the Availability check (checking group 02 in the standard system).

I have following levels of material in decending order with one to one relationship

Final product say M1

Semi finisher M2

Semi finshed M3

Raw mat M4

Now after doing the settings for strategy 11 in all the four material. When I am running mrp for M1 system is taking gross qty for plan order of M2 but it is not doing planning for lower levels though I have done the same settings for all levels.

What can be the reason for this?

Is there something I am doing wrong or am i missing something?

Please guide....

Regards,

Mayank