Skip to Content
0
Former Member
Sep 19, 2008 at 06:48 AM

confirmation for order

11 Views

Hi Experts,

please guide for the following,

SAP implementation is effective from 1st April-2008,

material consumed during this period is, directly posted to cost center by MM Consultant,

so,at the time of order confirmation,material are not in stock,or even it is in stock,issue of that material will double the cost,as it is already issued,

so now i can't do goods movement for the order,& hence completion,

suggest solution ,if there is any

thanks in advance