Hello All,

When I do cost estimate I am getting the error message as " no routing could be found with the selection criteria". Can any one please guide me where the problem is.

Thank you,

Nivas

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

5 Answers

  • Sep 19, 2008 at 06:18 AM

    Hi!

    There might be some missing areas in the master reciepe defined for the same. So, pls check the master recipe for the Material and resource combination.

    Hope it works.

    Thanks & Regards,

    Taral Patel

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 19, 2008 at 06:22 AM

    Hi,

    Please go to CA01 transaction code and create the Routing for that material with plant combination.

    Hope it helps

    Vijayanand Sankaran

    Add comment
    10|10000 characters needed characters exceeded

  • Sep 19, 2008 at 07:23 AM

    Dear Nivas,

    It seems no routing/Rate routing/recipe exists for the particular product for which you are trying to create a

    Cost Estimate.

    If you are into Discrete scenario then routing has to be created using T code CA01.

    If you are into REM scenario means then either routing /rate routing has to be created using T codes

    CA01/CA21.

    If you are into PP-PI Production Planning for Process Industries then you have to create the related one's.

    So kindly ask your PP person to create any one of the above and then do the cost calculation.

    Check & revert back.

    Regards

    Mangalraj.S

    Add comment
    10|10000 characters needed characters exceeded

  • Sep 19, 2008 at 08:37 AM

    Hi,

    selection depends on plant parameter tcode OPPQ

    Routing selection depends on

    1. Tasklist type

    2. Usage

    3. Status

    Please check in T code OPEB - regarding routing selection

    And also assign to order type in OPL8 Please check and come back?

    1. When you enter into the routing you give the Material plant group counter and date ..

    2.Check all the above inputs and correct them accordingly - since if you try to display a routing before the date it was created then it will give the above error

    So to retrive the erro

    1. Put the f4 in the groupnumber tab in ca03 - and search by material

    2. if the routing exitst then you can see them with a group number

    3. if the routing exitst then select them and clear the material plant etc and display the routing and check the validity date in the header screen

    4. from then when you want to access the routing give this date or clear the date in the selection screen and enter.

    Hope this will solve your issue.

    Regards,

    R.Brahmankar

    Add comment
    10|10000 characters needed characters exceeded

    • Hi,

      Routing selection and costing variant both they are assign to order type dependent parameter in OPL8? which is use in production order.

      Please check and come back for your order type and plant.

      Regards,

      R.Brahmankar

  • avatar image
    Former Member
    Sep 26, 2008 at 12:03 PM

    Combination of costing version,costing type, and valuation variant with Quntity structure type is missing in OKYD transaction, which is used to pick up the correct routing.