Former Member
0 Kudos

My company deliver stock/parts to multiple production lines. Some of the stock is used on all or some lines. Due to lack of experience within our plant, there is a lack of experience using SAP EWM. Anyway I have been put in charge of monitoring and improving the routing and layout as well as maintaining the the accuracy of inventory.

Anyway, I wish to have multiple fix bin assignments for one part but one storage bin only being allocated to one of the production lines without it creating tasks from the incorrect storage bin.

Could someone be able to explain how this could be done? If any more information is required please don't hesitate to ask and thanks in advance for your assistance.

Accepted Solutions (0)

Answers (0)