PS commitments does not match the PO receivings

Hi Dear Friends

We have a issue where PS commitments does not match the PO receivings

The problem is

using T- code "S_ALR_87013558 " to show the commitment of project

we find that the commitments are not getting reduced after GR

The PO 's have GR more than the commitment quantities, still the commitment is not zero.

Looking for pointers to resolve this,

Regards

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Sep 19, 2008 at 04:20 AM

    Dear,

    The goods receipt indicator in the purchase order determines when the commitment is reduced and actual costs are set up (that is, in the detail screen for the purchase order item).

    GR indicator set: Commitment is reduced when goods are received.

    GR Indicator is not set: Commitment is reduced when invoices are received.

    Regards.