Former Member

Difference between Capacity Baseload in CM07 and Capacity Availability Check

Hi,

the Problem is as follows:

Im having a difference in the capacity baseload of the Workplace "AROB" between the restults of the capacity availability check and when i check the results in the Transaction "CM07" with the baseload Profile "SAPSFC010".

Capacity availability check baseload:

CM07 baseload:

My questions are:

1. How is that possible?

2. Is there a way to check the results which capacity requirements result in the baseload in the capacity availability check results?

3. Where can i customize the result list in the capacity availaibility check? (e.g. that the unit is displayed in "H" and not "MIN")

4. How should a capacity planner now which base load is the correct one when he receives different baseloads in different views?

Thank you

zwwsu.png (23.9 kB)
w0mwn.png (6.9 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Apr 09 at 05:38 PM

    Hi Tobias

    If you are using the standard profile for capacity leveling, the problem may time horizon defined in the time profile. Try to create a custom profile, as a copy of the standard, extending the time periods.

    Try also the report RCCYLOAD to recalculate the work center basic load.

    Regards,

    Caetano