Hi All,

I have a custom Work flow in which I am trying to terminate a Decision Step via a terminating event.

Following Pre- requisites have been set:

1) In the Control task for the decision step I have assigned the terminating event.

2) Required linkages have been maintained via SWE3 transaction.

ISSUE: When the terminating event is raised then the Workitem for this steps gsts completed but workflow ends with an ERROR --> "No Successor for the terminating event defined".

Please let me know if any of you is familiar with the issue or have any inputs.

Thanks in advance..

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Sep 19, 2008 at 08:26 AM

    Hi Sourabh,

    There would be some binding problem going with Decision step while using Terminating event maintained at

    the Task of the Decision step.

    Rather go with FORK step with two parallel branch and 1 necessary branch. Specify the approval step in one

    branch and wait for the release step event in another branch.

    Hope this way would solve your issue.

    Good luck

    Narin

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.