09-18-2008 4:31 PM
Hi
I havea specific requirement for carrying out MR Validations -
Can I specifically ignore all the estimated reads from the reading history? And only check the current consumption against the consumption in a period between two Actual reads?
Any other workarounds to this?
09-19-2008 6:52 AM
Hai,
We have an answer for this.just check out this....
IMG>Device Management>Meter Reading>Basi settings>Define control parameters for Meter reading data processing
select ur company code and division
Go through the below two check boxes
Ignore estimations check box
Allow Estimated MRRs check box.
If not succedded use the below enhancement.
User exit control for estimation of results
If you select this field, enhancement EDMLELHA is triggered.
Regards,
Narendar Konakanchi
09-19-2008 5:53 AM
hi shabri
i hope ur requirement can be mapped with function modules regarding the meter reading
check the following fms specifically for meter reading
isu_meter_reading_rounding
isu_meter_data_format_check
and there are many more
just put isu_meter_* in search of se37
u will get the list..get assistance from abaper..i hope it will work through fms
regards
prince
09-19-2008 6:52 AM
Hai,
We have an answer for this.just check out this....
IMG>Device Management>Meter Reading>Basi settings>Define control parameters for Meter reading data processing
select ur company code and division
Go through the below two check boxes
Ignore estimations check box
Allow Estimated MRRs check box.
If not succedded use the below enhancement.
User exit control for estimation of results
If you select this field, enhancement EDMLELHA is triggered.
Regards,
Narendar Konakanchi