on 09-18-2008 4:18 PM
Hi All
My Client decided to change the Raw Materials to Semi finished. Can any body tell me how its gonna affect Product costing. I seems like I would need BOMs and Routings for every materail but what would be the direct impact on product cost ?
I would appreciate your early response.
Thanks
MKR
Hi,
1.Price control indicator in Material Master should "S" and Valuation class and any other change in Material master.
2.You have to have BOM and Routing for that particular materials.
3. After creating BOM and routings you have run material cost estimate(CK11N or CK40N) for that material.
Hope this helps.
Thanks,
Rau
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Changing the material type from one to another will not have any difference. Only in the process side, there will be some change like BOM/ Routing needs if the pricing control will become S and cost estimate has to be run.
Vijayanand Sankaran
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
96 | |
10 | |
9 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.