Dear All SAP Guru's

I have created one PO , in that stating to delivery at subcontractor and selecte the appropriate checkbox in the PO .After MIGO stock posted to subcontractor with movment type 101 O in quality .Our QM consultant release the inspection lot,he found that there is no stock to post to unresticted.And stock remains in the quality only after inspection lot cleared with UD.

Please suggest the solution.

Thanks and Regards

Mahesh Lotake

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Nov 19, 2008 at 06:43 AM

    not solved

    Add comment