PURCHASE REQUISSITION RELEASE STRATEGY

Dear All SAP Guru,

I have created purchase requisition release strategy in quality same as in devlopment(testing).In testing it is flowing correctly, but in quality when i created pr it is not added to release strategy.I checked everything characterstics, class, release startegy and found that it is very similar with testing client.I doesnot know where is problem.

Please suggest me solution

Thanks and regards

Mahesh Lotake

Add a comment
10|10000 characters needed characters exceeded

Related questions

6 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Sep 18, 2008 at 11:32 AM

    HI

    PR Release Stgy

    http://www.sap123.com/showthread.php?t=59

    Regards

    Ram

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Dear ALL SAP GURU's

      Got the solution and that was in the PR document type i have not select the overall pr rel check box , hence in the quality release strategy is not working.

      Thanks and Regards

      Mahesh Lotake

  • author's profile photo Former Member
    Former Member
    Posted on Sep 18, 2008 at 09:31 AM

    Have u maintained values in CL24N?

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Sep 18, 2008 at 10:23 AM

    Dear Mahesh Lotake,

    Sometime when you transport the DEV to QAS, you may missing the assignment value

    if you have not do it correctly. However you still can fill in the value manually. This

    can be done at CL24N -> and click the "Value of assignment" button. Also, make

    sure the status = 1(Active).

    You also need to check if any red trafic light to make sure you have no inconsistency.

    Execute the transaction OMGQCK or OMGSCK and ensure that the system does

    not show any red traffic lights.

    Best Regards,

    Ian Wong

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Sep 18, 2008 at 12:05 PM

    Hi,

    If you have transported the release strategy from dev. to quality, the values of the release strategy do not get transported to the target server. You have to maintain the values in the taget client.

    After maintaining the values, create PR or change existing PR (to change the value of PR). Then the release strategy will be applicable to PR.

    Regards,

    Prashant

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Sep 18, 2008 at 12:30 PM

    hi

    CT04 and CL02 are not transportable. Check char, and class or create again.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Sep 18, 2008 at 01:33 PM

    Dear

    Yes I have maintained the values in CL24N, still the problem is existing.

    Please suggest the solution

    Thanks and regards

    Mahesh lotake

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.