cancel
Showing results for 
Search instead for 
Did you mean: 

Scheduling agreement, unnecessary delivery schedule lines

Former Member
0 Kudos

Hello

We use Scheduling agreements for purchasing spare parts. The MRP run checks the warehouse requirements and creates delivery schedule line to scheduling agreement.

Now the MRP run creates unnecessary delivery schedule lines to scheduling agreement if the earlier created delivery schedule line's delivery date has been changed manually.

For example,

Today the MRP run finds requirement for one article and creates the delivery schedule line, where delivery date is 2.9.2008 (determined from articles basic data).

The Vendor confirms the delivery date as 3.10.2008 and the purchaser changes manually (transaction ME38) the delivery date to delivery schedule line accordingly and prints the created message.

The next MRP run creates new delivery schedule line, where delivery date is again 2.9.2008.

now there are two open delivery schedule lines for this article with delivery dates 3.10.2008 and 2.9.2008.

Why the MRP run does not notice the existing delivery schedule line with the new delivery date 3.10.2008?

we have changed delivery dates manually several years and this has never happened before.

could you please help me to resolve this.

Thanks in advance,

Srikanth

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member581212
Active Contributor
0 Kudos

hi,

These dates are internally defined from the planned del date, gr processing date drfined in MMR.....

Pls check the days there and change it as per your req....

hope it helps..

Regards

Priyanka.P

Former Member
0 Kudos

Hi Priyanka,

Thanks for the reply,

Actually problem is not in date,though allready there is a delivery schedule line, why MRP is creating new delivery schedule line once again...

former_member581212
Active Contributor
0 Kudos

In addition to the above post,

as you changed the date manually from 2nd to 3rd....

so there are was no report for 2nd generated ulitmately...and if generated it was changed...right...

so when you again run the mrp...the system will generate one more pr for the same article....

this ultimately happens because of the set del dates in the MMR as i told above..

Hope it helps..

Regards

Priyanka.P

Former Member
0 Kudos

Hi,

Check in source list whether field MRP has option 2 which creates automatic schedule lines.Kindly remove this.

regards

suresh

Former Member
0 Kudos

HI Priyanka,

But we have done these kind of date changes many times in the past, but this is the first time we are facing this problem....and also we have not done any changes in MMR....

Former Member
0 Kudos

Hi Suresh,

We are using automatic process only, we cant remove it.

here the problem is MRP run is creating unnecessary delivery schedule lines though allready there is a deilvery schedule exist for the material...this is happening after changing the delivery dat in the schedule.