Hi Experts,

Our client is having one more scenario......

Calibration of Test Equipments:

1. As per the schedule, Calibration Order will get generated and they do calibrate the Equipment. (This point I am very clear)

2. If the equipment doesn't fit into the required limits, they do send it outside. (here my doubt starts)

3. They do get it calibrated by external agency and they receive the equipment with test certificate.

My doubt is, is it possible to send the euipment by triggering a PR and PO through Califbration Order. Is it possible to include the equipment no in PO.

As per MM process, we can bring only materials to Store. So I think I have to have a Serial No assosiated with that Equipment.

If serial no profile is activated, will the system allow to receive the TEquip with the same serial no. (after repair. According to me, Valuation of the TE changes once that is repaired. So system will not allow). Also where and how to include Certificate of Vendor in this process.

Please suggest me the easier way to incorporate this scenario

Thnx in advance

Sam

Accepted Solutions (1)

Accepted Solutions (1)

former_member187991
Active Contributor
0 Kudos

hi

As you said kindly do the process of without serial number .just assign the material to that equipment ,then as standard send the material outside with respect to PO .in the material master make the procurement active with control key specified for test certificate

regards

thyagarajan

Former Member
0 Kudos

Thnx a Lot Mr.Thiyagarajan,

Do you mean to say, create the Test Equipment as a Material also. And attach the same Material to the Equipment through BOM.

Because the Test Equipment itself is given outside for Calibration. Then only I can avoid the Serial Number concep here.

(Other required settings in Material Master to be done). Is it correct.

Thnx in advance

Sam

former_member187991
Active Contributor
0 Kudos

hi

don't need to create BOM for equipment , yes you have to create a test equipment as material also .assign this material no in the equipment serial no tab page and do the rest of the process

regards

thyagarajan

Former Member
0 Kudos

Thanks a lot Mr.Thiyagarajan.

I will check the complete cycle with our MM team and I will update you.

Regards

Sam

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Sam,

I think that the way Sami had guided the solution to you is perfect.

You just need to incorporate a operation in your task list, having a control key same as PM02 which will trigger a PO for you. That may be a service PO. for which you can maintain the details according the "Service Entry sheet" Ask your MM guy for better explanation over the service entry sheet.

Regards,

Shyamal

Former Member
0 Kudos

Mr.Joshi,

What ever you have explained is correct, provided we dont want to capture the Material movement through PO and don't want to give the TE no in PO,

My requirement is to capture the TE no in PO.

Regards

Sam

Former Member
0 Kudos

Experts,

Please guide me

Sam

Former Member
0 Kudos

Hi

In task list operation you select the control key PM02 (- check with PM guy - it is external work)

and operation detail if you enter the vendor no (to whom you rented service or calibration)

once order released system will automatically generate the PR and then PO?

Inspection lot also generated__> once you receive the TE --> check the cerificate (for this you create 2 0r 3 MIC created eg. certicicate attached or not , calibrated or not etc)

make ud

let me know if you need further input

thanks

Sami