Scheduling agreement MRP run

Hi All,

We use Scheduling agreements for purchasing spare parts. The nightly MRP run checks the warehouse requirements and creates delivery schedule line to scheduling agreement.

Now the MRP run creates unnecessary delivery schedule lines to scheduling agreement if the earlier created delivery schedule line's delivery date has been changed manually.

Today the MRP run finds requirement for article XYZ and creates the delivery schedule line, where delivery date is 2.9.2008 (determined from articles basic data).

The Vendor confirms the delivery date as 3.10.2008 and the purchaser changes manually (transaction ME38) the delivery date to delivery schedule line accordingly and prints the created message.

The next MRP run creates new delivery schedule line, where delivery date is again 2.9.2008.

After that there are two open delivery schedule lines for article XYZ with delivery dates 3.10.2008 and 2.9.2008.

Why the MRP run does not notice the existing delivery schedule line with the new delivery date 3.10.2008?

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Nov 03, 2008 at 10:37 AM

    issue resolved

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.