controlling

Hi

I am getting following error in controlling .

You have not defined a CO account assignment for an account that is relevant to cost accounting.

System Response

Account 511001 is defined as a cost element.

This means that you must always specify a CO account assignment.

Procedure

Enter one of the following CO account assignments

Order

Cost center / cost center/ activity type

Sales order item (for a project or cost relevant)

Project / WBS element

Cost object (Process manufacturing)

Network/ Network activities

Business process

Profitability segment

Real estate object

The posting row affected is 0000000001, account 511001.

regards

cvs

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Sep 18, 2008 at 07:14 AM

    In your posting item, the CO account assignment is missing, I hope. Please input a relevant value like Cost centre, internal order, etc. That will solve your problem.

    Regards

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi,

      This is the HR-payroll posting error. i have already assign co object like cost center. could you give sugguestion.

      regards

      cvs