09-18-2008 6:04 AM
Hi All,
I have 3 Systems in my Landscape.
DEV-> QAS-> PRD
One of my Z program is running in the Production system.
This Z program is got deleted in the DEV and QAS.
How can I import the Program from Production System to QAS and DEV.
Regards,
Viji.
09-18-2008 6:09 AM
hi,
u can ask ur basis consultants to reimport the request from prd to devlopment and quality.
u can get request from E070 n E071 tables or utilities version management.
09-18-2008 6:09 AM
hi,
u can ask ur basis consultants to reimport the request from prd to devlopment and quality.
u can get request from E070 n E071 tables or utilities version management.
09-18-2008 6:20 AM
HI Gautham,
Whether the TR should be created in the Production and it need to be transported to QAS and DEV.
Is this is the way to Import the Program from Production System?
Regards,
Viji
09-18-2008 6:22 AM
09-18-2008 6:27 AM
09-18-2008 6:15 AM
hi Vijaya laxmi,
you can goto Production system ---> SE38/ SA38 and copy the program and create the same in program using SE38 in Development system and then transport it to Quality system.
You can also Re-Import the Request from Production to Dev system.
Thanks,
Nelson