Find the detail of a material cost CK13N

Former Member
0 Kudos

Hello:

I speak only a bit english so i hope that you can understand me.

I'm seeing the CK13N to look for a material cost. In this screen we have two tables. In the table of the down I see the cost element and its cost. But, this cost seem extranges and we need to investigate it.

¿How can we see the functions or process that SAP use to calculate this cost?

Thank you very much.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

You can see the Material Cost Estimate for the product inquestion through CK13N and it consists of Matrial cost and Labour Cost and Overhead Charges and other chanrges.You can see these components throgh assigned cost elements by clicking on the respective cost element.

Former Member
0 Kudos

Hello,

Thank you very much, Edukondalu Pericherla , for your anwser.

We know this transaction but the level of detail that it gives our isn't enought.

We need to have a deep analize to know the datail of ever components of CK13N. We need know the numbers of all lines.

We neet to know how is the process to calculate the materails cost.

Thank you very much.

Answers (1)

Answers (1)

former_member674271
Contributor
0 Kudos

Hi Jose,

The items in the down table are valuated from a strategy called valuation variant, which is in the costing variant you use for cost estimation. You can also branch from CK13N to view the costing variant then the valuation variant (or Tcode OKKN). The valuation variant defines the valuation strategy for material, activity type, and overhead, etc.

Items with M are material/semi-product consumption cost valuated from the material pricing strategy in the valuation variant and the material quantity in the product BOM.

Items with E are production cost valuated from activity type rate (Tcode KP26) and activity type quantity in the product Routing.

Items with G are overhead cost valuated by costing sheet. Usually it is calculated by a surcharge rate multiply the material consumption cost or production cost.

Wish this could help you