Skip to Content
avatar image
Former Member

what is the use of having process profiles in SPP?

Dear all,

what is the use of process profile in spp? it says we use it for specifying packaging methods and packaging sizes, but what are they used for?

can someone throw some light on it please?

regards,

binod

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Sep 22, 2008 at 02:22 PM

    Hi Binod,

    You define a process profile in Customizing for SCM Basis under Planning Service Manager ® Define Process Profile. A process profile includes a method for package creation and the maximum number of planning objects that a package can contain.

    This is one of the steps in creating a Planning Service Manager Jobs.

    If you setup a PSM job and run it then you get a clear idea.

    Please have a look at the below link:-

    http://help.sap.com/saphelp_scm2007/helpdata/en/42/cc2978ebc16bb1e10000000a1553f6/frameset.htm

    Thanks,

    KD

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Nov 12, 2008 at 07:44 PM

    Hi Binod

    As you might know, the Process Profile is one of the intermediate steps in a Planning Run in SPP. The planning run is executed in the Planning Service Manager and could be used to run Inventory Balancing, DRP, Deployment, Supersession etc.,

    One of the steps in the execution of the planning run is to create Selections. Selections could be for example by Products, Locations, Product Locations, Transportation Lanes etc., From the selection we get the total number of Product Locations. The value you set in the Process Profile for "Max. Pack Size" determines how many of these Product Location Combination values would be processed when each package is created.

    Have I answered your question? Please let me know!

    Regards

    Sam

    SAP America

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Sam,

      I would like to know how can you set up or send the planning data from APO to ICH or SNC.

      I want your help in letting me know the configuration steps for sending the DP and DRP data.

      I am working on the new implementation project of SNC , I need to read the data from APO - DP and DRP. so want to the initial steps for reading the data from DRP and DP.

      Kindly help me.

      Ramya.