Skip to Content

Planned order showing different date in SNP Planning book and product view

Hello Experts,

I am new to SAP APO. Need help!!!

I execute the Location heuristic for location and product combination. It generates Planned orders also.

But when I check the date in Product view, it is showing different date for the same planned order.

I was expecting the same date as shown in planning book. Please help.

Thanks

Rakesh

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    May 07 at 01:59 PM

    Hello Rakesh,

    Can you set the time zone accordingly which can be found in settings tab in the Product view (tx. /sapapo/rrp3) properly and recheck the scenario.

    Best Regards

    Manish


    Add comment
    10|10000 characters needed characters exceeded