on 09-17-2008 10:39 AM
Hi Friends,
I am getting following error message while specifying the Caledar Id in Rebate Agreement.
System response as follows:
*The system only permits a calendar as a settlement period if the workdays in the calendar fall at the end of the period.*
Suggest me how should I avoid this message.
Regards,
Tirumalasetti
Dear Tirumalasetti,
This may be due to there is holiday in that calendar on the date of the Rebate agreement period end date.
So please change the Rebate agreement period end date or change holiday to working day in that calendar on that date.
I this will help you,
Regards,
Murali.